Project:        
    Provision of External HT Connection to S & T Bn.Div.
    Battle School & Medium WKsp (Ph-II)-  Pano Aqil Cantt.
    Client:
    Military Engineering Services (MES)
    Dated:
    24-02-1988
    Scope:
    The project was to extend the 11 KV underground 3
    core 95 mm sq. XLPE 95 mm sq. Cable loop to provide
    Electricity to Army installation. NMC performed the job
    within time and to the utmost satisfaction of the client,
    and hence many more projects were awarded to NMC by
    MES.
.................................................................................................................................
    Project:        
    Provision of HT/LT Distribution & Street Light in S & T
    Bn.(Ph-II), Pano Aqil Cantt.
    Client:
    Military Engineering Services (MES)
    Dated:
    12-01-1988
    Scope:
    Comprising of XPLE 3 Core 11 KV 150 mm sq. Cable
    Underground Feeders on Main Avenue and Overhead
    Distribution network to provide Electricity to Army
    Installation.
.................................................................................................................................
    Project:        
    Provision of External Electrification to 192 Married OR
    Quarters, Gujranwala Cantt.
    Client:
    Military Engineering Services (MES)
    Dated:
    12-04-1986
    Scope:
    This was a project of external electrification comprising
    of 11 KV Ring main and underground distribution system
    to Army Residences. The project was awarded by
    Military Engineering Services and was completed within
    time.  
.................................................................................................................................
    Project:        
    External Electrification of Millat Town , Faisalabad.
    Client:
    Faisalabad Development Authority (FDA)
    Dated:
    14-04-1983
    Scope:
    F.D.A is developing Housing Schemes around the main
    city of Faisalabad to settle the population problem.
    Millat Town is one of the schemes. This Town is being
    develop over a total area of 3 Millions Sq. metres and
    we are executing its Electrification Job. The Scope of
    work comprises of construction of 11 KV/LT. overhead
    Distribution, Lines, Poles Mounting out-door Sub-
    Station, Street /Garden Lighting, etc. We managed to
    complete the entire job six months earlier than the
    scheduled date.

.................................................................................................................................
    Project:        
    Internal/External Electrification Of Dir Forest Industries
    Complex Chakdara, Thatta, Sindh.
    Client:
    Pakistan Industrial Development Corporation (PIDC)
    Dated:
    23-10-1982
    Scope:
    P.I.D.C., an autonomous body of the Government of the
    Pakistan has been established to develop the industry in
    the country. Dir Forest industries complex at Chakdara in
    District Dir is one of its major Projects. The
    corresponding machinery for Plywood, Chip Board
    Section, Saw Mills, Boiler House, Mechanical Work shop
    and Tower Cranes was imported from M/S POLIMEX-
    CEKOP, Poland. The entire electrification and
    Automization job of the Machinery and external
    Electrification of Factory and Housing Colony was
    satisfactory carried out by us. The customers and polish
    experts appreciated our technical know-how and found
    our work upto their entire satisfaction.
.................................................................................................................................
<< Previous, 1, 2, 3, 4, 5 ... , Next >>
    Project:        
    Industrial Electrification of a Factory in P.O.Fs Godwal,
    Wah Cantt
    Client:
    Pakistan Ordnance Factories (POF)
    Dated:
    05-10-1980
    Scope:
    This was a classified project. The assignment of national
    importance comprised of extension of H.T. Line, Two H.
    T. Cable feeders, H.T./ L.T. panels, power factor
    improvement plant, power cables, Generating sets, L.T.
    Distribution Boards, Lighting system, Earthing and
    Lighting protection which were completed within the
    specified time. The recommendation of the client on
    completion of this project is an asset of the company
    .
.................................................................................................................................
    Project:        
    Internal/External Electrification Of Thatta Sugar Mills
    Client:
    Sindh Sugar Corporation Ltd.
    Dated:
    19-09-1979
    Scope:
    The government of Sind established an autonomous
    body “Sind Sugar Corporation Ltd.” to develop Sugar
    Mills in Sind Province. The corporation set up two sugar
    Mills, one at Dadu and other ion Thatta. We were
    entrusted with the job of electrification of Thatta Sugar
    Mills project. We undertook complete Sub-station work,
    supply of Power to Mill, Housing Colony, Rest House and
    offices. The Steam Power Station was also set up in the
    Mill. This Plant along with Electrical Equipments was
    imported from France. We also carried out the Electrical
    Work of French material, and gained good experience in
    setting up Sugar industries including its atomization. We
    erected, tested, commissioned and handed over the
    project to the client up-to his entire satisfaction.
.................................................................................................................................
    Project:        
    External Electrification of Wah Industries (New Shot Gun
    Ammo Factory)
    Client:
    WAH Industries
    Dated:
    11-09-1981
    Scope:
    Wah Industries Limited (WIL) is the only manufactured of
    12 Bore Shot Gun Ammunition. The cartridges
    “Shaheen’ are very popular both in home and abroad.
    M/S WIL set up a new plant imported from Belgium to
    increase the production and improve the quality. The
    Electrification of New Shot Gun Ammunition Factory
    covers construction of overHead Line on Tubular Poles,
    Hard drawn Bare Copper Conductor, Power cables, Light
    Wiring and accessories, Distribution Boards and Panels,
    Earthing System, Lighting protection and Security
    Network. On the timely and excellent execution of the
    Electrical Network, the client entrusted in Toto and
    recommended nmc for all important future Projects of
    Pakistan Ordinance Factories.
.................................................................................................................................
    Project:        
    Internal/External Electrification of Trainuing-Cum-
    Constuction Centre, Dera Ghazi Khan
    Client:
    National Highway Board, Islamabad
    Dated:
    15-02-1981
    Scope:
    The government of Pakistan planned to construct a
    Super Highway for connecting Karachi with Peshawar in
    order to reduce 200 KM distance between the two big
    cities. Five training cum construction centre were
    developed for the repair of imported road machinery. A
    modern housing colony, Rest House, Hostel, Mosque,
    and other services also built up. We were awarded the
    Electrification Work of D.G Khan centre. The scope of
    work comprised of supply and installation of all material
    such as H.T./L.T. structures, All Alminium and ACSR
    conductors, insulators, Light Fixture, Power Cables,
    Control Panels, Sub Station Equipments, D.Bs., Earthing
    Strips and conductors.        
.................................................................................................................................
    Project:        
    Supply and Erection of L.T. Tubular Poles, Over
    Headlines and Lights on the Road Linking the Plant Site
    to Colony Dera Ghazi Khan
    Client:
    Atomic Energy Commission (PAEC)
    Dated:
    07-05-1980
    Scope:
    For effective security measures the entire roads, linking
    residential colony to plant site was to be illuminated. For
    this purpose, an economical system comprising of
    tubular poles fabricated out of high frequency electrical
    resistance welded tubes of various diameter and All
    Aluminum Stranded conductor was proposed. The
    system was erected, commissioned and handed over to
    P.A.E.C., which is giving satisfactory service.
.................................................................................................................................
Since 1976